Project
County of Newell, Alberta — Brooks–Tilley area
An off-grid, wellhead-adjacent gas-to-compute site on Canada's east–west arteries: the Trans-Canada Highway 1 and the CP Rail mainline, with Alberta SuperNet fiber passing nearby.
Status
Approvals complete, Phase 1 operational, Phase 2 underway
Phase 2 rack build-out, compute commissioning and expansion are underway internally.
Government Approval
Land reclassification · Building permit · EA cleared
Phase 1 · Commissioned
Site · Power distribution · Generation online
Phase 2 · Compute Hall
Rack build-out · Commissioning · Underway
Location
Brooks–Tilley area · wellhead-adjacent
Technical & Construction Plan
30 × 400 kW skid-mounted gas gensets, replicated to scale
Phase 1 delivers 10 MW; Phase 2 replicates the same module to add +40 MW for a planned 50 MW total.
Phase 1 · nameplate
12 MW
30 × 400 kW gas gensets, 10 MW continuous COP.
Phase 2 · expansion
+40 MW
Same module replicated toward a planned 50 MW.
Generation
Emissions control
Electrical distribution
Halls, cooling & fiber
Construction flow
- Step 1
Gas assessment & purchase contract → land lease
- Step 2
Municipal building permit & land reclassification → EA / noise / emissions compliance
- Step 3
Site civil & electrical works → genset transport, install & power connection
- Step 4
Data-center operations (ERP production safety, EMS emergency shutdown) → waste-heat recovery for green cultivation
Delivery cadence (equipment): after down payment and finalization, the first shipment begins in ~3 weeks, shipping weekly, with Phase 1 equipment delivered within ~4 weeks.
Development Timeline
Approvals → generation → rack build-out → commissioning → expansion
Approvals complete
CompleteLand reclassification, municipal building permit and EA cleared.
Generation operational
CompletePhase 1 site, power distribution and generation online and commissioned.
Rack build-out underway
In progressPhase 2 compute hall rack build-out and equipment installation in progress.
Commissioning
In progressCompute commissioning and operations build-up (ERP safety plan / EMS shutdown).
Expansion
PlannedReplicate the module to expand toward 50 MW; waste-heat circulation planned.
Construction progress detail
Work-item status as reported in the project overview.
- Gas assessment, commercial negotiation, gas purchase contract signedDone
- Land acquisition, land lease signedDone
- Municipal building permit, land reclassificationDone
- Government EA, noise assessment, emissions compliance, building permitDone
- Phase 1 site design, civil & electrical works, interconnectionDone
- Phase 1 genset installation & generation (commissioned)Done
- Phase 2 rack build-out, compute equipment install & commissioningIn progress
- Phase 2 expansion civil works & power-distribution build-outIn progress
- Operations build-up (ERP safety plan / EMS shutdown)In progress
- Waste-heat recovery, green cultivation (extension)Planned
Site Photography
Generation, power distribution and the compute hall
Photographs of the operating facility and construction progress at the Alberta site.






Implementation Roadmap
Four staged milestones
- Stage 1 — Government approval and land acquisition / lease, land reclassification.
- Stage 2 — Phase 1 10 MW build and production, with mining as base-load cash flow.
- Stage 3 — Expand to 50 MW in Phase 2; acquire gas supply to optimize cost; waste-heat circulation for green cultivation.
- Stage 4 (optional) — Land AI-compute offtake and RWA asset tokenization.
Reviewing the site for capital or compute offtake?
We can walk through approvals, generation data, hall layout and the expansion plan in a preliminary discussion.